New Connection Procedure
1. Customer applies for private water connection at WUC front offices. Required documents to be attached to the application forms:
o Proof of ownership (title deed/certificate of land rights)
o Certified copy of Omang (Citizens) or Passport (Non-Citizens)
2. Customer requested to come back or call after 7 working days for quotation.
3. After receiving the quotation, customer pays
4. Water supply is connected to customer’s plot